Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.22 | 3.22 | 0.000 | 3.22 | 3.220 | 0.000 |
No of Bridges | 2 | 2 | 2 | 0 | 0 | 0 |
52W385 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2076/।।।(2)/20-47(प्रा0आ0)/ 2016 दिनंाक 24 नवम्बर 2020
TS Amount (lakhs) : 275.63 Lacs
Financial Detail
Sanction Cost : 275.63 Lacs
Resanction Cost : 275.63 Lacs
Exp. Upto Last Fy : 205.71 Lacs
For CFY 2024-2025
Remaining : 69.92 Lacs
Demand : 70.03 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 205.71 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
3 years 5 months ago
24 Nov 2020
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का 3.22 कि.मी. कार्य पूर्ण । सेतु का 90 प्रतिशत कार्य पूर्ण, शेष कार्य प्रगति पर है। -- as on 10-Apr-2024
Physical Peramenters