Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 60 | 60 | 0.000 | 60 | 0.000 | 0.000 |
52W390 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-1383/।।।(2)/21-30(प्रा0आ0)2017 टी.सी. दिनांक 21.05.2021 द्वारा रू0 8.40 लाख की स्वीकृति प्राप्त।
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 8.40 Lacs
Resanction Cost : 8.40 Lacs
Exp. Upto Last Fy : 6.79 Lacs
For CFY 2024-2025
Remaining : 1.61 Lacs
Demand : 0.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6.79 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 11 months ago
21 May 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्र्थम चरण कार्य पूर्ण द्वितीय चरण की डी.पी.आर.मुख्य अभि0 क्षेत्रीय कार्यालय लो0नि0वि0,देहरादून के पत्रांक सं0-31292/09(86) याता0(क्षे0का0)/2022 दिनांक 31.05.2023 द्वारा आगणन आपत्तियों में वापस, जिनका निराकरण वृत्तीय कार्यालय में कर दिया गया है। -- as on 05-Jan-2024
Physical Peramenters