Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 2.000 | 2 | 2.000 | 0.000 |
52W519 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-ई पत्रावली संख्या-45425,लोक निर्माण अनुभाग-2,देहरादून दिनांक 24 जुलाई 2023
TS Amount (lakhs) : 140.76 Lacs
Financial Detail
Sanction Cost : 145.01 Lacs
Resanction Cost : 140.76 Lacs
Exp. Upto Last Fy : 39.27 Lacs
For CFY 2024-2025
Remaining : 101.49 Lacs
Demand : 101.49 Lacs
Allotment : 5.67 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 39.27 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 months 3 weeks ago
24 Jul 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 06-Mar-2024