Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 2.000 | 2 | 2.000 | 1.000 |
52W519 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-ई पत्रावली संख्या-45425,लोक निर्माण अनुभाग-2,देहरादून दिनांक 24 जुलाई 2023
TS Amount (lakhs) : 140.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
145.01
Resanction Cost :
140.76
Tentative Cost :
140.76
Exp. Upto Last Fy : 39.27
For CFY 2024-2025
Remaining : 101.49
Demand : 101.49
Allotment : 17.88
Exp in CFY : 1.56
Total Up to Date Exp : 40.83
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 70 %
Sanction on :
11 months 3 weeks ago
24 Jul 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
कुछ ग्रामीणों द्वारा वनविभाग को शिकायत कर कार्यस्थल पर कार्य रूकवा दिया गया है। जिसके निस्तारण की कार्यवाही गतिमान है। -- as on 11-Jul-2024
Physical Peramenters