Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.800 | 4.2 | 4.200 | 0.800 |
52W522 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 ई0 पत्रावली-35334 लोक निर्माण अनुभाग-2,देहरादून दिनांक 07/08/2023
TS Amount (lakhs) : 143.24 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
143.24
Resanction Cost :
143.24
Tentative Cost :
143.24
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 143.14
Demand : 135.00
Allotment : 32.20
Exp in CFY : 21.68
Total Up to Date Exp : 21.78
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 60 %
Sanction on :
11 months 1 week ago
07 Aug 2023
Tentative Completion date:
10 months 3 weeks ago
25 Aug 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3 कि 0 मी 0 पहाड़ कटान का कार्य पूर्ण,शेष कार्य प्रगति पर है| -- as on 13-Jul-2024
Physical Peramenters