Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18.46 | 18.46 | 0.000 | 18.46 | 18.460 | 0.000 |
52W524 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता,(विभागाध्यक्ष) लोक निर्माण विभाग,देहरादून के पत्रांक सं0-895ध्07याता0-पी.एम.जी.एस.वाई.-नियोजन -।।। दिनाक 16.05.2023
TS Amount (lakhs) : 75.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
75.58
Resanction Cost :
75.58
Tentative Cost :
75.58
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 75.58
Demand : 75.58
Allotment : 35.95
Exp in CFY : 35.95
Total Up to Date Exp : 35.95
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 50 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
4 months 1 day from now
19 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्लिप सफाई का कार्य पूर्ण । शेष कार्य प्रगति पर । -- as on 28-Jun-2024
Physical Peramenters