Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 2.000 | 6 | 6.000 | 0.000 |
52W527 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता,(विभागाध्यक्ष) लोक निर्माण विभाग,देहरादून के पत्रांक सं0-895ध्07याता0-पी.एम.जी.एस.वाई.-नियोजन -।।। दिनाक 16.05.2023
TS Amount (lakhs) : 87.54 Lacs
Financial Detail
Sanction Cost : 87.54 Lacs
Resanction Cost : 87.64 Lacs
Exp. Upto Last Fy : 18.16 Lacs
For CFY 2024-2025
Remaining : 69.48 Lacs
Demand : 69.48 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 18.16 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
5 months 4 weeks from now
19 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 12-Apr-2024
Physical Peramenters