Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 22.63 | 22.63 | 9.000 | 13.63 | 13.630 | 0.000 |
52W528 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : कार्यालय प्रमुख अभियन्ता,(विभागाध्यक्ष) लोक निर्माण विभाग,देहरादून के पत्रांक सं0-895ध्07याता0-पी.एम.जी.एस.वाई.-नियोजन -।।। दिनाक 16.05.2023
TS Amount (lakhs) : 142.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
142.35
Resanction Cost :
142.35
Tentative Cost :
142.35
Exp. Upto Last Fy : 28.15
For CFY 2024-2025
Remaining : 114.20
Demand : 114.20
Allotment : 77.27
Exp in CFY : 77.27
Total Up to Date Exp : 105.42
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 90 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
1 month 3 weeks from now
10 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डामरीकरण का कार्य पूर्ण , ड्रैन कि सफाई ऍवं पटरी फिलिंग का कार्य प्रगति पर है। -- as on 28-Jun-2024
Physical Peramenters