Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
Span of Bridges [m] | 18 | 18 | 0.000 | 18 | 0.000 | 0.000 |
52W532 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-ई पत्रावली संख्या-45425 लोक निर्माण अनुभाग-2,देहरादून दिनांक 27 अक्टूबर 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 11.22 Lacs
Resanction Cost : 11.22 Lacs
Exp. Upto Last Fy : 0.09 Lacs
For CFY 2024-2025
Remaining : 11.13 Lacs
Demand : 2.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.09 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 3 weeks ago
27 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य पूर्ण,समेरखण हेतु पत्रावली गठित करने की कार्यवाही गतिमान है। -- as on 08-Mar-2024
Physical Peramenters