Work Profile Report [52W536]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-ई पत्रावली संख्या-45425लोक निर्माण अनुभाग-2,देहरादून दिनांक 29 नवम्बर 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.67
Resanction Cost :
40.67
Tentative Cost :
40.67
Exp. Upto Last Fy :
5.08
For CFY 2024-2025
Remaining :
35.59
Demand :
35.59
Allotment :
33.35
Exp in CFY :
33.35
Total Up to Date Exp :
38.43
Work completed
Sanction on : 1 year 3 weeks ago
29 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
70 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
माह 09/2024 में कार्य पूर्ण | -- as on 26-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: