Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.925 | 2.925 | 0.000 | 2.925 | 2.920 | 0.000 |
52W536 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-ई पत्रावली संख्या-45425लोक निर्माण अनुभाग-2,देहरादून दिनांक 29 नवम्बर 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 40.67 Lacs
Resanction Cost : 40.67 Lacs
Exp. Upto Last Fy : 5.08 Lacs
For CFY 2024-2025
Remaining : 35.59 Lacs
Demand : 35.59 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5.08 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
5 months 2 weeks ago
29 Nov 2023
Tentative Completion date:
4 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर हैं| -- as on 29-Apr-2024
Physical Peramenters