Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 155.89 | 155.89 | 128.000 | 27.89 | 27.890 | 0.000 |
52W538 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2451/।।। /(2)/23-01(प्रा.आ.)/2019 लोक निर्माण अनुभाग-2,देहरादून दिनांक 21 जुलाई 2023
TS Amount (lakhs) : 1298 Lacs
Financial Detail
Sanction Cost : 1,298.00 Lacs
Resanction Cost : 1,298.00 Lacs
Exp. Upto Last Fy : 904.16 Lacs
For CFY 2024-2025
Remaining : 393.84 Lacs
Demand : 393.84 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 904.16 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 83 %
Sanction on :
9 months 4 weeks ago
21 Jul 2023
Tentative Completion date:
1 month 1 day from now
21 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 12-Jan-2024
Physical Peramenters