Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 155.89 | 155.89 | 128.000 | 27.89 | 27.890 | 0.000 |
52W538 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2451/।।। /(2)/23-01(प्रा.आ.)/2019 लोक निर्माण अनुभाग-2,देहरादून दिनांक 21 जुलाई 2023
TS Amount (lakhs) : 1298 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1298.00
Resanction Cost :
1298.00
Tentative Cost :
1298.00
Exp. Upto Last Fy : 904.16
For CFY 2024-2025
Remaining : 393.84
Demand : 393.84
Allotment : 393.84
Exp in CFY : 211.12
Total Up to Date Exp : 1,115.28
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 85 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
3 weeks 5 days ago
21 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 12-Jan-2024
Physical Peramenters