Work Profile Report [52W540]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0-5082/।।। /(2)/23-01(प्रा.आ.)/2019 लोक निर्माण अनुभाग-2,देहरादून दिनांक 09 नवम्बर 2023
TS Amount (lakhs) : 482.36 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
482.36
Resanction Cost :
482.36
Tentative Cost :
482.36
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
482.36
Demand :
482.36
Allotment :
342.18
Exp in CFY :
91.77
Total Up to Date Exp :
91.77
Technical sanction done
Sanction on : 1 year 1 month ago
09 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
70 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 04-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: