Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.67 | 5.67 | 5.670 | 0 | 0.000 | 0.000 |
53W1386 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1267/।।।(2)/19-19 (एम0एल0ए0)/2017 दिनांक 07.03.2019
TS Amount (lakhs) : 451.97 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
451.97
Resanction Cost :
485.01
Tentative Cost :
485.01
Exp. Upto Last Fy : 452.43
For CFY 2024-2025
Remaining : 32.58
Demand : 21.28
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 452.43
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
07 Mar 2019
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
3 years 9 months ago
01 Oct 2020
Remark
Bottelneck: no issue
कार्य माह 12/2020 में पूर्ण। कार्य डी0एल0पी0 में चल रहा है। -- as on 01-May-2024
Physical Peramenters