Work Profile Report [53W1401]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 1643/।।।(3)/2019-35 (सी0आर0एफ0)/ 2019 दिनांक 07.11.2019
TS Amount (lakhs) : 509.6 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
509.60
Resanction Cost :
509.60
Tentative Cost :
509.60
Exp. Upto Last Fy :
441.56
For CFY 2025-2026
Remaining :
68.04
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
441.56
Work completed
Sanction on : 6 years 1 week ago
07 Nov 2019
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 3 years 7 months ago
31 Mar 2022
Actual Completion Date : 4 years 8 months ago
01 Mar 2021
Physical Linear Components
Remark
मार्ग कार्य माह 03/2021 में पूर्ण। नाली का कार्य प्रगति पर है। -- as on 30-May-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI: RCC Arch bridge