Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.35 | 7.35 | 7.350 | 0 | 0.000 | 0.000 |
53W1487 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 213/।।।(2)/ 21-23 (एम.एल.ए.)/2017 दिनांक 11.02.2021
TS Amount (lakhs) : 433.28 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
433.28
Resanction Cost :
495.33
Tentative Cost :
495.33
Exp. Upto Last Fy : 456.78
For CFY 2024-2025
Remaining : 38.55
Demand : 38.54
Allotment : 38.55
Exp in CFY : 13.19
Total Up to Date Exp : 469.97
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 5 months ago
11 Feb 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
2 years 3 months ago
31 Mar 2022
Remark
Bottelneck: no issue
कार्य माह 03/2022 में पूर्ण। कार्य पर 14.32 प्रतिशत आधिक्य का प्रस्ताव मुख्य अभियन्ता क्षे0का0 देहरादून के पत्रांक 2394/09(388)याता0-स्तर-। (क्षे0का0)/2020 दिनांक 27.09.2023 द्वारा रू0 62.05 लाख का स्वीकृत। -- as on 01-May-2024
Physical Peramenters