Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.15 | 5.15 | 5.150 | 0 | 0.000 | 0.000 |
53W1490 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : एन.एच.ए.आई./पी.आई.यू.-10/पी.डब्लू.डी./27 दिनांक 24.12.2020
TS Amount (lakhs) : 349.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
349.91
Resanction Cost :
349.91
Tentative Cost :
349.91
Exp. Upto Last Fy : 318.56
For CFY 2024-2025
Remaining : 31.35
Demand : 31.35
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 318.56
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 6 months ago
24 Dec 2020
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
2 years 3 months ago
31 Mar 2022
Remark
Bottelneck: no issue
कार्य माह 05 /2022 मे पूर्ण। -- as on 28-Jul-2022
Physical Peramenters