Work Profile Report [53W1495]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2804/।।।(2)/19-01(एम.पी.)/2019 दिनांक 30.07.2019
TS Amount (lakhs) : 267.3 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
285.34
Resanction Cost :
256.81
Tentative Cost :
256.81
Exp. Upto Last Fy :
253.81
For CFY 2025-2026
Remaining :
3.00
Demand :
3.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
253.81
In Maintenance After Completion
Sanction on : 6 years 4 months ago
30 Jul 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 2 weeks ago
31 Mar 2025
Actual Completion Date : 4 years 2 months ago
30 Sep 2021
Physical Linear Components
Remark
कार्य माह 03/21 में नाबार्ड-26 में स्वीकृत हुआ है। कार्य माह 06/21 में पूर्ण। कार्य डी0एल0पी0 में चल रहा है। -- as on 01-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: