Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.4 | 1.4 | 1.400 | 0 | 0.000 | 0.000 |
53W1500 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1558/।।।(2)/21.19 (एम.एल.ए.) 2017 दिनांक 15.06.2021
TS Amount (lakhs) : 132.71 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
132.71
Resanction Cost :
132.71
Tentative Cost :
132.71
Exp. Upto Last Fy : 116.79
For CFY 2024-2025
Remaining : 15.92
Demand : 15.92
Allotment : 15.92
Exp in CFY : 8.20
Total Up to Date Exp : 124.99
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
15 Jun 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
10 months 2 weeks ago
31 Aug 2023
Remark
Bottelneck: no issue
कार्य माह 08/2023 में पूर्ण। -- as on 08-Sep-2023