Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.034 | 3.5 | 2.300 | 1.2 | 1.200 | 0.000 |
53W1519 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1708/।।।(2)/21-19 (एम0एल0ए0)2017 दिनांक 17.06.2021
TS Amount (lakhs) : 323.5 Lacs
Financial Detail
Sanction Cost : 161.75 Lacs
Resanction Cost : 161.75 Lacs
Exp. Upto Last Fy : 152.92 Lacs
For CFY 2024-2025
Remaining : 8.83 Lacs
Demand : 8.80 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 152.92 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
2 years 11 months ago
17 Jun 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.30 किमी0 लम्बाई में कार्य पूर्ण। अवशेष कार्य प्रगति पर है। -- as on 09-Apr-2023
Physical Peramenters