Work Profile Report [53W1523]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2356/।।।(2)/21-03(प्रा0आ0)2018 दिनांक 02.08.2021
TS Amount (lakhs) : 135.92 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
135.92
Resanction Cost :
135.92
Tentative Cost :
135.92
Exp. Upto Last Fy :
130.97
For CFY 2024-2025
Remaining :
4.95
Demand :
4.95
Allotment :
4.95
Exp in CFY :
0.85
Total Up to Date Exp :
131.82
Work completed
Sanction on : 3 years 3 months ago
02 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य माह 07/2023 में पूर्ण। -- as on 01-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand