Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.55 | 4.55 | 3.950 | 0.6 | 0.600 | 0.000 |
53W1529 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2396/।।।(2)/21-19(एम0एल0ए0)2017 दिनांक 04.08.2021
TS Amount (lakhs) : 80.22 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
80.22
Resanction Cost :
80.22
Tentative Cost :
80.22
Exp. Upto Last Fy : 79.01
For CFY 2024-2025
Remaining : 1.21
Demand : 1.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 79.01
Construction Started
Physical Progress:
At start of FY 2024-2025 : 86 %
Up to Date : 86 %
Sanction on :
2 years 11 months ago
04 Aug 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
एस0डी0बी0सी0 का कार्य माह 02/2022 में पूर्ण। इण्टरलाॅकिग का कार्य प्रगति पर है। -- as on 25-May-2022