Work Profile Report [53W1529]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2396/।।।(2)/21-19(एम0एल0ए0)2017 दिनांक 04.08.2021
TS Amount (lakhs) : 80.22 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
80.22
Resanction Cost :
80.22
Tentative Cost :
80.22
Exp. Upto Last Fy :
79.01
For CFY 2024-2025
Remaining :
1.21
Demand :
1.20
Allotment :
1.20
Exp in CFY :
0.00
Total Up to Date Exp :
79.01
Construction Started
Sanction on : 3 years 4 months ago
04 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
86 %
Up to Date :
86 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
एस0डी0बी0सी0 का कार्य माह 02/2022 में पूर्ण। इण्टरलाॅकिग का कार्य प्रगति पर है। -- as on 25-May-2022