Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.026 | 2.026 | 2.026 | 0 | 0.000 | 0.000 |
53W1534 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2396/।।।(2)/21-19(एम0एल0ए0)2017 दिनांक 04.08.2021
TS Amount (lakhs) : 92.86 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
92.86
Resanction Cost :
92.86
Tentative Cost :
92.86
Exp. Upto Last Fy : 91.18
For CFY 2024-2025
Remaining : 1.68
Demand : 1.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 91.18
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
04 Aug 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
1 year 3 months ago
31 Mar 2023
Remark
Bottelneck: no issue
कार्य माह 06/2022 में पूर्ण। -- as on 28-Jul-2022