Work Profile Report [53W1536]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2396/।।।(2)/21-19(एम0एल0ए0)2017 दिनांक 04.08.2021
TS Amount (lakhs) : 92.82 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
92.82
Resanction Cost :
92.82
Tentative Cost :
92.82
Exp. Upto Last Fy :
37.51
For CFY 2024-2025
Remaining :
55.31
Demand :
55.00
Allotment :
55.00
Exp in CFY :
1.12
Total Up to Date Exp :
38.63
Work completed
Sanction on : 3 years 3 months ago
04 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date : 1 year 7 months ago
31 Mar 2023
Physical Linear Components
Remark
कार्य माह 12/2022 में पूर्ण। -- as on 09-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand