Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 30 | 30 | 0.000 | 30 | 0.000 | 0.000 |
53W1547 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3219/।।।(2)/21-24 (एम.एल.ए.)2017 दिनांक 27.08.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 6.88 Lacs
Resanction Cost : 6.88 Lacs
Exp. Upto Last Fy : 1.71 Lacs
For CFY 2024-2025
Remaining : 5.17 Lacs
Demand : 5.17 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.71 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
2 years 8 months ago
27 Aug 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वे कार्य पूर्ण। सेतु के स्थल चयन का कार्य पूर्ण। डी0पी0आर0 गठित कर जाॅच हेतु डिजाईन सैल को प्रेषित। -- as on 01-May-2024
Physical Peramenters