Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.83 | 4.83 | 4.830 | 0 | 0.000 | 0.000 |
53W1553 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5687/।।।(2)/21-19(एम.एल.ए.)2017 दिनांक 23.11.2021
TS Amount (lakhs) : 131.58 Lacs
Financial Detail
Sanction Cost : 131.58 Lacs
Resanction Cost : 131.58 Lacs
Exp. Upto Last Fy : 129.11 Lacs
For CFY 2024-2025
Remaining : 2.47 Lacs
Demand : 2.40 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 129.11 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 5 months ago
23 Nov 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
एस0डी0बी0सी0 का कार्य माह 12/2022 में पूर्ण। इण्टर लाॅकिग टाईल्स का कार्य माह 04/2023 में पूर्ण। -- as on 11-May-2023
Physical Peramenters