Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.97 | 4.97 | 4.970 | 0 | 0.000 | 0.000 |
53W1554 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6026/।।।(2)/21-19(एम.एल.ए.)2017 टी0सी0 दिनांक 14.12.2021
TS Amount (lakhs) : 139.99 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
139.99
Resanction Cost :
139.99
Tentative Cost :
139.99
Exp. Upto Last Fy : 122.05
For CFY 2024-2025
Remaining : 17.94
Demand : 17.90
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 122.05
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
14 Dec 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
एस.डी.बी.सी. का कार्य माह 06/2023 में पूर्ण। अवशेष टाईल्स के स्थान पर एस0डी0बी0सी0 का कार्य करवाया गया। कार्य माह 03/2024 में पूर्ण। -- as on 01-May-2024
Physical Peramenters