Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.97 | 4.97 | 4.640 | 0.33 | 0.330 | 0.000 |
53W1555 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 6026/।।।(2)/21-19(एम.एल.ए.)2017 टी0सी0 दिनांक 14.12.2021
TS Amount (lakhs) : 114.37 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
114.37
Resanction Cost :
114.37
Tentative Cost :
114.37
Exp. Upto Last Fy : 101.95
For CFY 2024-2025
Remaining : 12.42
Demand : 12.40
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 101.95
Construction Started
Physical Progress:
At start of FY 2024-2025 : 74 %
Up to Date : 74 %
Sanction on :
2 years 7 months ago
14 Dec 2021
Tentative Completion date:
11 months 2 weeks ago
29 Jul 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इण्टरलाॅकिग टाईल्स का कार्य प्रगति पर है। -- as on 08-Sep-2023
Physical Peramenters