Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
53W1578 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी देहरादून का पत्रांक 861/जि0यो0-लो0नि0वि0/2022-23 दिनांक 17-10-2022
TS Amount (lakhs) : 12 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
12.00
Resanction Cost :
12.00
Tentative Cost :
12.00
Exp. Upto Last Fy : 4.11
For CFY 2024-2025
Remaining : 7.89
Demand : 7.89
Allotment : 7.45
Exp in CFY : 6.89
Total Up to Date Exp : 11.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 9 months ago
17 Oct 2022
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य माह 02/2024 में पूर्ण। -- as on 05-Mar-2024
Physical Peramenters