Work Profile Report [53W1612]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी देहरादून का पत्रांक 861/जि0यो0-लो0नि0वि0/2022-23 दिनांक 17-10-2022
TS Amount (lakhs) : 12 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
12.00
Resanction Cost :
12.00
Tentative Cost :
12.00
Exp. Upto Last Fy :
11.76
For CFY 2025-2026
Remaining :
0.24
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
11.76
Work completed
Sanction on : 2 years 8 months ago
17 Oct 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 hours ago
31 Mar 2025
Actual Completion Date : 11 months 1 day ago
30 Jul 2024
Physical Linear Components
Remark
कार्य माह 07/2024 में पूर्ण। -- as on 02-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: