Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
53W1627 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन, देहरादून की ई पत्रावली संख्या 48224 दिनांक 15.02.2023
TS Amount (lakhs) : 330.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
330.87
Resanction Cost :
330.87
Tentative Cost :
330.87
Exp. Upto Last Fy : 297.04
For CFY 2024-2025
Remaining : 33.83
Demand : 33.83
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 297.04
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 5 months ago
15 Feb 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
1 year 1 month ago
31 May 2023
Remark
Bottelneck: no issue
कार्य माह 05/2023 में पूर्ण। -- as on 06-Jun-2023
Physical Peramenters