Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15.02 | 15.02 | 8.000 | 7.02 | 7.020 | 0.000 |
53W1634 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन, देहरादून की ई पत्रावली संख्या 49284 दिनांक 29.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 398.13 Lacs
Resanction Cost : 398.13 Lacs
Exp. Upto Last Fy : 226.15 Lacs
For CFY 2024-2025
Remaining : 171.98 Lacs
Demand : 170.00 Lacs
Allotment : 60.00 Lacs
Exp in CFY : 0.32 Lacs
Total Up to Date Exp : 226.47 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 1 month ago
29 Mar 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है । -- as on 05-Dec-2023