Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.38 | 1.38 | 1.000 | 0.38 | 0.380 | 0.000 |
53W1635 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन, देहरादून की ई पत्रावली संख्या 50232 दिनांक 31.03.2023
TS Amount (lakhs) : 97.99 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
97.99
Resanction Cost :
97.99
Tentative Cost :
97.99
Exp. Upto Last Fy : 46.75
For CFY 2024-2025
Remaining : 51.24
Demand : 51.00
Allotment : 20.00
Exp in CFY : 3.35
Total Up to Date Exp : 50.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 72 %
Up to Date : 80 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
3 weeks 2 days from now
10 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0एस0बी0, जी3 एवं इण्टरलाॅकिंग लगाये जाने का कार्य प्रगति पर है। -- as on 29-Jun-2024