Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.565 | 1.565 | 1.000 | 0.565 | 0.560 | 0.000 |
53W1638 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन, देहरादून की ई पत्रावली संख्या 50232 दिनांक 31.03.2023
TS Amount (lakhs) : 99.59 Lacs
Financial Detail
Sanction Cost : 99.59 Lacs
Resanction Cost : 106.96 Lacs
Exp. Upto Last Fy : 40.79 Lacs
For CFY 2024-2025
Remaining : 66.17 Lacs
Demand : 58.80 Lacs
Allotment : 10.23 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 40.79 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
500 मीटर लम्बाई में मार्ग का कार्य पूर्ण। अवशेष लम्बाई में कार्य प्रगति पर है। कार्य माह 09/2023 में नाबार्ड में लागत रू0 106.96 लाख का स्वीकृत हुआ है। जिसमें रू0 10.70 लाख राज्यांश एवं रू0 7.37 लाख डी.एल.पी. सम्मिलित है। -- as on 06-Mar-2024
Physical Peramenters