Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 4.900 | 0.1 | 0.100 | 0.000 |
53W1642 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1708/।।।(2)/21-19 (एम0एल0ए0)2017 दिनांक 17.06.2021
TS Amount (lakhs) : 122.38 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
130.30
Resanction Cost :
130.30
Tentative Cost :
130.30
Exp. Upto Last Fy : 120.81
For CFY 2024-2025
Remaining : 9.49
Demand : 1.57
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 120.81
Construction Started
Physical Progress:
At start of FY 2024-2025 : 98 %
Up to Date : 98 %
Sanction on :
2 years 11 months ago
02 Aug 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.90 किमी0 लम्बाई में कार्य पूर्ण। 100 मीटर लम्बाई में कास्तकारों द्वारा मुआवजे के विवाद के कारण कार्य बाधित है। कास्तकारों से वार्ताकर विवाद को सुलझाया जा रहा है -- as on 01-May-2024
Physical Peramenters