Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.745 | 0.745 | 0.740 | 0.005 | 0.000 | 0.000 |
53W1654 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 54048 दिनांक 14.07.2023
TS Amount (lakhs) : 46.47 Lacs
Financial Detail
Sanction Cost : 46.47 Lacs
Resanction Cost : 46.47 Lacs
Exp. Upto Last Fy : 21.35 Lacs
For CFY 2024-2025
Remaining : 25.12 Lacs
Demand : 25.10 Lacs
Allotment : 25.00 Lacs
Exp in CFY : 0.31 Lacs
Total Up to Date Exp : 21.66 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 months 5 days ago
14 Jul 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य माह 03/2024 में पूर्ण। -- as on 01-May-2024
Physical Peramenters