Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24.65 | 24.65 | 4.650 | 20 | 20.000 | 0.000 |
53W1656 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0 पत्रावली संख्या 49284 दिनांक 31.07.2023
TS Amount (lakhs) : 748.32 Lacs
Financial Detail
Sanction Cost : 748.32 Lacs
Resanction Cost : 748.32 Lacs
Exp. Upto Last Fy : 205.50 Lacs
For CFY 2024-2025
Remaining : 542.82 Lacs
Demand : 542.82 Lacs
Allotment : 100.00 Lacs
Exp in CFY : 0.69 Lacs
Total Up to Date Exp : 206.20 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 year 10 months from now
31 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 07-Jan-2024
Physical Peramenters