Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 24.65 | 24.65 | 4.650 | 20 | 20.000 | 0.000 |
53W1656 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0 पत्रावली संख्या 49284 दिनांक 31.07.2023
TS Amount (lakhs) : 748.32 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
748.32
Resanction Cost :
748.32
Tentative Cost :
748.32
Exp. Upto Last Fy : 205.50
For CFY 2024-2025
Remaining : 542.82
Demand : 542.82
Allotment : 200.00
Exp in CFY : 201.11
Total Up to Date Exp : 406.61
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 65 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
7 months 3 weeks from now
11 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0एस0बी0, जी3 एवं इण्टरलाॅकिंग लगाये जाने का कार्य प्रगति पर है। मार्ग पर इण्टरलाॅकिग टाईल्स के स्थान पर 400 मीटर अतिरिक्त एस0डी0बी0सी0 का कार्य करवाया गया है। -- as on 04-Jul-2024
Physical Peramenters