Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.46 | 2.46 | 0.600 | 1.86 | 1.860 | 0.000 |
53W1658 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0 पत्रावली सं0 46690 दिनांक 07/08/2023
TS Amount (lakhs) : 116.97 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
116.97
Resanction Cost :
116.97
Tentative Cost :
116.97
Exp. Upto Last Fy : 39.35
For CFY 2024-2025
Remaining : 77.62
Demand : 77.50
Allotment : 20.00
Exp in CFY : 25.44
Total Up to Date Exp : 64.79
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 57 %
Sanction on :
11 months 1 week ago
07 Aug 2023
Tentative Completion date:
3 weeks 5 days from now
13 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0एस0बी0, जी3 एवं इण्टरलाॅकिंग लगाये जाने का कार्य प्रगति पर है। -- as on 29-Jun-2024
Physical Peramenters