Work Profile Report [53W1658]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई0 पत्रावली सं0 46690 दिनांक 07/08/2023
TS Amount (lakhs) : 116.97 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
116.97
Resanction Cost :
116.97
Tentative Cost :
116.97
Exp. Upto Last Fy :
39.35
For CFY 2024-2025
Remaining :
77.62
Demand :
77.50
Allotment :
70.00
Exp in CFY :
69.06
Total Up to Date Exp :
108.41
Work completed
Sanction on : 1 year 3 months ago
07 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
26 %
Up to Date :
100 %
Tentative Completion date on : 3 months 1 week ago
13 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य माह 08/2024 में पूर्ण। -- as on 04-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand