Work Profile Report [53W1658]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई0 पत्रावली सं0 46690 दिनांक 07/08/2023
TS Amount (lakhs) : 116.97 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
116.97
Resanction Cost :
116.97
Tentative Cost :
116.97
Exp. Upto Last Fy :
119.70
For CFY 2025-2026
Remaining :
-2.73
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
119.70
Work completed
Sanction on : 2 years 3 months ago
07 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 months ago
13 Aug 2024
Actual Completion Date : 1 year 2 months ago
30 Aug 2024
Physical Linear Components
Remark
कार्य माह 08/2024 में पूर्ण। -- as on 04-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand