Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.46 | 2.46 | 0.600 | 1.86 | 1.860 | 0.000 |
53W1658 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई0 पत्रावली सं0 46690 दिनांक 07/08/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 116.97 Lacs
Resanction Cost : 116.97 Lacs
Exp. Upto Last Fy : 39.35 Lacs
For CFY 2024-2025
Remaining : 77.62 Lacs
Demand : 77.50 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.20 Lacs
Total Up to Date Exp : 39.54 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
9 months 1 week ago
07 Aug 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 07-Jan-2024
Physical Peramenters