Work Profile Report [53W1661]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी कार्यालय का पत्रांक 1445/प्र0ना0सदर-2023 (पी0एन0बी0/समारोह) दिनांक 18.09.2023
TS Amount (lakhs) : 214.51 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
214.51
Resanction Cost :
214.51
Tentative Cost :
214.51
Exp. Upto Last Fy :
85.00
For CFY 2024-2025
Remaining :
129.51
Demand :
129.51
Allotment :
0.00
Exp in CFY :
86.05
Total Up to Date Exp :
171.05
Work completed
Sanction on : 1 year 2 months ago
18 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य जी-20 सम्मेलन से पूर्व माह 06/2023 में पूर्ण करवा दिया गया था। -- as on 06-Oct-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: