Work Profile Report [53W1665]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 50232 दिनांक 13.10.2023
TS Amount (lakhs) : 130.25 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
130.25
Resanction Cost :
130.25
Tentative Cost :
130.25
Exp. Upto Last Fy :
0.87
For CFY 2024-2025
Remaining :
129.38
Demand :
120.00
Allotment :
100.00
Exp in CFY :
51.95
Total Up to Date Exp :
52.82
Construction Started
Sanction on : 1 year 2 months ago
13 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
35 %
Tentative Completion date on : 1 month 1 week from now
06 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है । -- as on 15-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: