Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.95 | 1.95 | 0.000 | 1.95 | 1.950 | 0.000 |
53W1665 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 50232 दिनांक 13.10.2023
TS Amount (lakhs) : 130.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
130.25
Resanction Cost :
130.25
Tentative Cost :
130.25
Exp. Upto Last Fy : 0.87
For CFY 2024-2025
Remaining : 129.38
Demand : 120.00
Allotment : 20.00
Exp in CFY : 0.40
Total Up to Date Exp : 1.27
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 7 %
Sanction on :
9 months 4 days ago
13 Oct 2023
Tentative Completion date:
6 months 2 weeks from now
06 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्थानीय निवासियों द्वारा विवाद किया जा रहा है। -- as on 04-Jul-2024
Physical Peramenters