Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.95 | 1.95 | 0.000 | 1.95 | 1.950 | 0.000 |
53W1665 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 50232 दिनांक 13.10.2023
TS Amount (lakhs) : 130.25 Lacs
Financial Detail
Sanction Cost : 130.25 Lacs
Resanction Cost : 130.25 Lacs
Exp. Upto Last Fy : 0.87 Lacs
For CFY 2024-2025
Remaining : 129.38 Lacs
Demand : 120.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.40 Lacs
Total Up to Date Exp : 1.27 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
7 months 6 days ago
13 Oct 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
नाली निर्माण का कार्य प्रगति पर है। -- as on 01-May-2024
Physical Peramenters