Work Profile Report [53W1670]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी देहरादून के पत्रांक 1279 जि0यो0-लो0नि0वि0 2023-24 दिनांक 16.10.2023
TS Amount (lakhs) : 8 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8.00
Resanction Cost :
8.00
Tentative Cost :
8.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
8.00
Demand :
8.00
Allotment :
7.83
Exp in CFY :
3.10
Total Up to Date Exp :
3.10
Work completed
Sanction on : 1 year 2 months ago
16 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य माह 09/2024 में पूर्ण । -- as on 15-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: