Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.034 | 1.034 | 0.000 | 1.034 | 1.030 | 0.000 |
53W1689 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई पत्रावली सं0 24012 दिनांक 25.09.2023
TS Amount (lakhs) : 41.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.58
Resanction Cost :
41.58
Tentative Cost :
41.58
Exp. Upto Last Fy : 2.47
For CFY 2024-2025
Remaining : 39.11
Demand : 39.00
Allotment : 30.00
Exp in CFY : 18.51
Total Up to Date Exp : 20.97
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 49 %
Sanction on :
9 months 3 weeks ago
25 Sep 2023
Tentative Completion date:
4 months 1 week from now
25 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0एस0बी0, जी3 एवं इण्टरलाॅकिंग लगाये जाने का कार्य प्रगति पर है। -- as on 29-Jun-2024
Physical Peramenters