Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 37.85 | 37.85 | 0.000 | 37.85 | 0.000 | 0.000 |
53W1693 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0ं 212/।।।(2)/2024-01 (प्रा0आ0)/2023 दिनांक 31.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
312.45
Resanction Cost :
312.45
Tentative Cost :
312.45
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 312.45
Demand : 312.00
Allotment : 160.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठन की प्रक्रिया गतिमान है। -- as on 08-Jul-2024
Physical Peramenters