Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.675 | 3.675 | 0.000 | 3.675 | 0.000 | 0.000 |
No of Bridges | 2 | 2 | 0 | 2 | 0 | 0 |
Span of Bridges [m] | 30 | 30 | 0.000 | 30 | 0.000 | 0.000 |
53W1700 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेेश ई पत्रावली सं0 43324 दिनांक 19.02.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
12.18
Resanction Cost :
12.18
Tentative Cost :
12.18
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 12.18
Demand : 12.00
Allotment : 0.50
Exp in CFY : 0.07
Total Up to Date Exp : 0.07
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
4 months 4 weeks ago
19 Feb 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
मेप व हवाई दूरी प्रमाणपत्र प्राप्त किये जा रहे हंै तथा भूवैज्ञानिक की आख्या प्राप्त की जा रही है। -- as on 31-May-2024
Physical Peramenters