Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.27 | 4.27 | 4.27 | 0 |
54W1007 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2178(1)/।।।(2)/20-17 (एम0एल0ए0)/2017, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 04.12.2020
TS Amount (lakhs) : 166.17 Lacs
Financial Detail
Sanction Cost : 166.17 Lacs
Resanction Cost : 178.63 Lacs
Exp. Upto Last Fy : 162.39 Lacs
For CFY 2024-2025
Remaining : 16.24 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 162.39 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 5 months ago
04 Dec 2020
Tentative Completion date:
1 year 6 months ago
15 Nov 2022
Actual Completion Date:
1 month 2 weeks ago
31 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। कार्य अनुरक्षण के अन्तर्गत है। -- as on 08-Apr-2024
Physical Peramenters