Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 3 | 3 | 3 | 0 |
54W1037 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1697(1)/।।।(2)/21-1 (प्रा0आ0)/2020, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 16.06.2021
TS Amount (lakhs) : 10.12 Lacs
Financial Detail
Sanction Cost : 10.12 Lacs
Resanction Cost : 10.12 Lacs
Exp. Upto Last Fy : 9.41 Lacs
For CFY 2024-2025
Remaining : 0.71 Lacs
Demand : 0.71 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 9.41 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
2 years 11 months ago
16 Jun 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 08-Mar-2024
Physical Peramenters