Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.966 | 4.96 | 4.96 | 0 |
54W1066 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2565(1)/।।।(2)/21-16 (एम0एल0ए0)2017, टी0सी0-।, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 05.08.2021
TS Amount (lakhs) : 236.73 Lacs
Financial Detail
Sanction Cost : 236.73 Lacs
Resanction Cost : 252.04 Lacs
Exp. Upto Last Fy : 236.74 Lacs
For CFY 2024-2025
Remaining : 15.30 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 236.74 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
05 Aug 2021
Tentative Completion date:
1 year 5 months ago
03 Dec 2022
Actual Completion Date:
1 month 2 weeks ago
31 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। कार्य अनुरक्षण के अन्तर्गत है। -- as on 08-Apr-2024
Physical Peramenters