Work Profile Report [54W1080]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0- 1111(।)/।।।(3)/2021-38 (सी0आर0आई0एफ0)2021, लोक निर्माण अनुभाग-3, देहरादून, दिनांक 04.10.2021
TS Amount (lakhs) : 135.09 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
135.09
Resanction Cost :
135.09
Tentative Cost :
135.09
Exp. Upto Last Fy :
135.09
For CFY 2024-2025
Remaining :
0.00
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
135.09
Work completed
Sanction on : 3 years 1 month ago
04 Oct 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 2 years 7 hours ago
27 Nov 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 14-Dec-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3
Bridges on The Basis of AI: Box Culvert
© PWD Uttarakhand