Work Profile Report [54W1104]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-463/।।।(2)/22-16 (एम0एल0ए0) /2017, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 07.01.2022
TS Amount (lakhs) : 206.07 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
206.07
Resanction Cost :
206.07
Tentative Cost :
206.07
Exp. Upto Last Fy :
141.49
For CFY 2024-2025
Remaining :
64.58
Demand :
64.58
Allotment :
64.27
Exp in CFY :
64.27
Total Up to Date Exp :
205.75
Work completed
Sanction on : 2 years 10 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 9 months 1 week ago
10 Feb 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 08-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand