Work Profile Report [54W1105]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-458/।।।(2)/22-21 (एम0एल0ए0)/ 2017 टी0सी0आई0, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 07.01.2022
TS Amount (lakhs) : 233.29 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
233.29
Resanction Cost :
233.29
Tentative Cost :
233.29
Exp. Upto Last Fy :
220.37
For CFY 2024-2025
Remaining :
12.92
Demand :
12.92
Allotment :
12.41
Exp in CFY :
12.41
Total Up to Date Exp :
232.78
Work completed
Sanction on : 2 years 10 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 8 months ago
28 Feb 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 10-Mar-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand