Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.99 | 4.99 | 4.990 | 0 | 0.000 | 0.000 |
54W1106 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-458/।।।(2)/22-21 (एम0एल0ए0)/ 2017 टी0सी0आई0, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 07.01.2022
TS Amount (lakhs) : 233.99 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
233.99
Resanction Cost :
233.99
Tentative Cost :
233.99
Exp. Upto Last Fy : 225.86
For CFY 2024-2025
Remaining : 8.13
Demand : 8.13
Allotment : 5.16
Exp in CFY : 5.15
Total Up to Date Exp : 231.02
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
2 years 5 days ago
12 Jul 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष है। -- as on 05-Aug-2023
Physical Peramenters