Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
54W1107 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 52ध्।।।(3)ध्2021-07 (एन0एच0)2016, लोक निर्माण अनुभाग-3, देहरादून, दिनांक 12.01.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 4,315.57 Lacs
Resanction Cost : 4,315.57 Lacs
Exp. Upto Last Fy : 3,350.00 Lacs
For CFY 2024-2025
Remaining : 965.57 Lacs
Demand : 965.57 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 3,350.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
3 years 4 months ago
12 Jan 2021
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य एन0एच0ए0आई0 के द्वारा करवाया जा रहा है। कार्य की भौतिक प्रगति 55 प्रतिशत है। -- as on 08-Apr-2024
Physical Peramenters